Who are considered "Stakeholders" in a project?

  1. Individuals solely responsible for technical delivery

  2. Anyone with an interest in the project outcome

  3. Only the project managers

  4. Team members who are not involved in planning

The correct answer is: Anyone with an interest in the project outcome

Stakeholders in a project are defined as anyone who has an interest in the project's outcome. This broad definition encompasses a wide range of individuals and groups, including team members, project sponsors, customers, end-users, suppliers, and other parties who may be affected by the project or can influence its execution. Recognizing all stakeholders is crucial for effective communication and collaboration throughout the project lifecycle, as their input and feedback can significantly impact decisions and the overall success of the project. Understanding that the concept of stakeholders goes beyond just the immediate project team is essential in Agile practices. This inclusivity ensures that varying perspectives and needs are considered, leading to more informed decision-making and increased chances for stakeholder satisfaction with the final product. In contrast, the other options are too narrow, focusing solely on specific roles rather than the broader community involved in or affected by the project.